Accent Wall Material Checklist
For a dry area feature wall such as a bathroom wall, entry, bar, or bedroom wall. Not a wet area.
How to use this list
- Mark every Buy item Have it, Still need, or Not for my job.
- Tick each Decide item once you have made the call.
- Shop from the Still need list at the top. Print it if that helps.
- When everything is delivered, confirm it here and Tony sets your start date.
0 of 9 items ready
Your answers are saved in this browser.
Still need to buy
Nothing marked Still need.
Buy
Feature tile
Square footage plus 15%, plus 20% for herringbone, diagonal, or large format tile. One order, one dye lot. Large format and patterned tile need the 20%.
Status: Not answered
Buy
Single dye lot confirmed
Check the lot number on every box. They must match.
Status: Not answered
Buy
Edge trim or metal edge profile, with finish
Accent walls almost always have exposed edges.
Status: Not answered
Buy
Outlet and switch box extenders
One for every box on the wall.
Status: Not answered
Decide
Grout color
Picked from our sample board against your tile. We supply the grout.
Status: Not answered
Decide
Coverage
Full wall, partial height, or a framed panel.
Status: Not answered
Decide
Where the pattern is centered
Status: Not answered
Decide
Wall cleared of TVs, shelves, and art by start day
Status: Not answered
Decide
Lighting or electrical changes
If any, done by your electrician before we start.
Status: Not answered
Order these first
These take the longest. Order them as soon as you book.
- The tile itself, in one order and one dye lot.
- Trim or metal edge profiles. The most forgotten item.
- Special order or imported tile.
Typical lead times
| Item | Lead time | When to order |
|---|---|---|
| In stock porcelain or ceramic | 3 to 7 days | Order 2 weeks before start |
| Special order tile | 2 to 6 weeks | Order when booked |
| Imported or handmade tile | 4 to 12 weeks | Order before we set a date |
| Natural stone | 2 to 8 weeks | Order when booked |
| Metal edge profiles | 1 to 3 weeks | Order with the tile |
| Heated floor mat | 1 to 3 weeks | Order 2 weeks before start |
| Custom glass through our partner | 2 to 3 weeks | Measured after grout |
Lead times are typical Columbus ranges, not a quote.
Other checklists
Kitchen Backsplash Checklist
The lightest list. Tile, trim, and a few small parts.
Open the list
Tile Floor Checklist
Tile, transitions, and the heated mat decision you cannot make later.
Open the list
Custom Shower Checklist
Full tear out and rebuild. The heaviest list, so start here early.
Open the list
Shower Walls Only Checklist
Keeping your shower base or pan? Here is what to have on site for new wall tile.
Open the list
Tub Surround Checklist
Walls, trim, and the tub decision before we set a date.
Open the list
Fireplace Surround Checklist
Surround tile, hearth, and how far up the wall it goes.
Open the list
Aging in Place Shower Checklist
Everything in the shower list, plus grab bars, traction, and access.
Open the list
Ready for a quote?
Free written estimate. Most jobs take 2 to 3 days once materials are here.